Some road construction here in Springfield:

* Relocate Weaver at Campbell 450 feet north of its current location. The new section of Weaver will tie in to the existing road about 800 feet on both sides of Campbell.

* Widen Weaver on both sides of Campbell to provide dual left-turn lanes on Weaver.

* Build dual left-turn lanes on southbound Campbell Avenue to eastbound Weaver Road.

* Build a new box culvert for Ward Branch Creek under Weaver west of Campbell; Weaver will be closed at the creek during that part of the project.

* Build new sidewalks along Weaver and a new Campbell pedestrian crossing on the south side of the new intersection.

* Build connections from the new section of Weaver to the old road to provide access to businesses, homes and apartments.

* Install new traffic signals and street lighting at the new intersection

Sounds complicated, but don’t worry: experienced, qualified engineers are on it:

The lead contractor on the project is D & E Plumbing and Heating, Inc. of Nixa, doing the work for a low bid amount of $4.3 million. The project is scheduled for completion by Dec. 1, 2011.